The first step is to have a Septic System Feasibility Study performed on the property to determine if the site perks and if it does what type system the Health District is going to require; This Study costs $ 250.00.

 

The next step is to apply for and acquire approval of a “Critical Area’s Ordinance” site plan from the King County Building Dept. They can do this for you if you desire, or you can hire your own consultant such as John Altmann with Altmann Oliver Associates LLC 425-333-4535 john@altoliver.com  or Kim Peterson of Blue Heron Services 360-793-7767 bheron@premier1.net

 

Note for property located within a City's Limits, the CAO Review must still be done and approved by the City. A copy of the letter from the City will need to be submitted with the Septic System Design Application to the Health District.

 

After you have CAO approval for the site, then we can revisit the site and prepare the full septic system design and submit it to the Health District for their review and approval; The Septic Design will cost

$ 1,500.00 (note that this amount is in addition to the $ 250.00 paid for the feasibility study; the design cannot be done without doing the feasibility study first) with an additional Health District Design Review fee of between $ 455.00 – 1,026.00;

It will take us about a week to prepare the Septic Design; The Health District will take between 10-16 weeks to review it; Once approved it will be valid for two years.

Note that prior to Septic Design Submittal to the Health District several paperwork items will need to be provided by you:
 
1. If the property is served by Public Water, then a Current "Certificate Of Water Availability" will need to be produced. Contact the water purveyor for this.
 
2. If the property is to be served by an Individual Well, then the "Declaration Of Covenant - Individual Water Supply" will need to be filled in, signed by the property owner in front of a Notary Public, recorded at the King County Administration Building in Seattle, then forwarded to us for inclusion with the Septic Design Submittal Package. Note that we can help you with this paperwork.
 
3. If the property is to be served by a Group "B" Water System then you should contact the water system controller to verify that the water system is up to date and can sustain another connection. We will need the official name and id number for the water system for the septic design submittal.

Note: If you need assistance with the above, please feel free to contact us.
 