Camp Agnolo - Retention Wall

Home
Tow Vehicle
The 5th Wheel
Fulltiming
Camp Agnolo
My RV Products
Links
Happiness
RV Tools
Gallery
Chronology
Site Map

CampagnoloText.jpg

Building the Wall the First Time
 
After the road was at finish grade, it became obvious that we would need a retaining wall of some kind. There are two springs in the sand seam that were exposed once the road was cut in.

DrivewaySpring.JPG
Spring #1

DrivewaySeamSpring.jpg
Spring #2

SandSeam.jpg
Sand Seam

Hargraves excavation, a company that Dad had a long history with, was hired to build the retention wall for ~$9000. They ran over budget by ~$4000 and produced this wall in the late fall of 2008.

CampAgnoloWallTop.jpg
Top Edge

CampAgnoloWallFullView.jpg
Full View

CampAgnoloWallBottom.jpg
Bottom Edge

Spring of 2009
 
The spring thaw of 2009 caused a few issues. Mainly, the wall collapsed. It looks like there was no run to daylight provision for the water behind the wall and there was no fabric separating the silt from the base stone so silt quickly filled the gaps in the previous fall. In the winter, this all froze and created an ice dam that prevented the springs from draining. In the spring, when it thawed, the dirt behind the wall became a slurry and blew out the lower stones of the stack wall. (The original plan called for a riprap wall.)

CAWallCollapse.jpg
Complete Wall Collapse

Painful Side Effects
 
When the wall collapsed, it clogged the drainage ditch and sent a wall of silt across the access road, into the county storm water system and plugged my sluice pipe and the sluice that passes under the roadway.
 
This in turn got a complaint filed with the NYSDEC by some county supervisor. Why the county couldn't talk to me first, I don't know. I guess there are people who work, then there are bureaucrats.
 
After a two sleepless nights and forced learning, a new engineered wall was designed, approved by the state, and ready for construction. This is the wall that I paid to be built the first time. The excuse of "I can't control nature" handed out by the contractor put them on my "never hire again" list.

masterwallassysidejpg.jpg
Drawing Side View

masterwallassyfrontjpg.jpg
Drawing Front View

The new engineered wall has a footer of block stones in the 2500 lb. range, about 6' horizontal depth of #6 light stone fill separated from the dirt with landscape fabric. Under the light stone fill will be a cloth wrapped drain to channel water to daylight. The top surface layer will be proper riprap using 1500 lb. base stones and fill stones as small as #6 light fill stone.

Rebuilding the Retaining Wall
 
Before the wall can be properly rebuild, it needs to be deconstructed. All of stones have been pulled out of the wall and stacked on the side of the access road. Tremendous thunderstorms have pounded the area for weeks. We will need to have a few dry weeks before we can start major reconstruction.

WallDeconstructed.jpg
Stones On the High Side

LowerWallDeconstruction.jpg
Stones on the Low Side

Rebuilding the wall has to be complete by 12/15/2009 as per the SWPPP and my agreement with the NYSDEC. Demolition was only the first step.

Building the Wall, Version 2.0
 
Construction on the second incarnation of the retaining wall started on 7/31/2009. Two solid days with our small backhoe, a rented Bobcat, and a generous logging truck got the base, drainage pipe, and the first course of stone set in place.
 
First Weekend Progress:

WallFooter.jpg
Base Profile

RiprapBase.jpg
First Course

LowerWall20.jpg
Bottom Edge

Over Labor Day weekend (2009), we placed another set of large stones. Prior to placing the stones, 60 tons of #6 light stone fill was placed behind the first row. This makes 140 tons of #6 light stone fill. I anticipate another 40 tons going into place before we are done.
 
To get the #6 into place, drivealbe access was constructed on the high side of the wall. It's hard to get proper perspective on how massive this retaining wall actually is.
 
Labor Day 2009 Progress:

WallDrivableAccess.jpg
Drivable Access

WallSizePerspective.jpg
Size Perspective

WallStoneFillSept09.jpg
#6 Light Stone Fill

SeptWallPan1.jpg
Wall Far Left

SeptWallPan2.jpg
Wall Center Left

SeptWallPan3.jpg
Wall Center Right

SeptWallPan4.jpg
Wall Right

Over Columbus Day weekend (2009), we placed the final set of large stones. Prior to placing the stones, and additional 60 tons of #6 light stone fill was placed behind the top row. This makes 200 tones of #6 light stone fill. We are done with #6 light stone fill.
 
Columbus Day 2009 Progress:

LowerDriveVegetation.jpg
Vegetative Cover

BigStonesWholeWall.jpg
Big Stones All Done

WallFabricCap.jpg
Fabric Cap

BigStonesDone1.jpg
Wall Far Left

BigStonesDone2.jpg
Wall Center Left

BigStonesDone3.jpg
Wall Center Right

BigStonesDone4.jpg
Wall Right

By Thanksgiving weekend (2009), the wall was complete. The dirt cap is in place, and all of the locking stones have been placed into the gaps. In the spring, we'll seed the top cap with grass. As long as it survives the winter freeze thaw cycle, we'll be good.
 
Complete, Thanksgiving 2009:

Final09WallProfile.jpg
Final Profile

Final09RetainWall.jpg
From the Top

Final09RetainWallLower.jpg
From the Bottom

Final09Wall1.jpg
Wall Far Left

Final09Wall2.jpg
Wall Center Left

Final09Wall3.jpg
Wall Center Right

Final09Wall4.jpg
Wall Right

Copyright 2006-2010 All Rights Reserved